Should Flooring Go Under Kitchen Cabinets?

Meet the author

Patrick leads the in-person experience at BluePrint Cabinets, helping homeowners and contractors plan their kitchens from the first showroom visit to the final measurements. With years of experience in the cabinet industry, he’s spent hundreds of hours working through real kitchen layouts, solving design challenges, and making sure cabinets fit the way they should in real homes.
DIY & Assembly Updated November 2026 · 9 min read

Kitchen cabinets should generally be installed before floating vinyl plank and laminate flooring, but can often be installed over tile, nail-down hardwood and fully adhered vinyl flooring.

The correct installation order depends on the flooring manufacturer’s requirements, expansion gaps, finished floor height and appliance clearances.

At BluePrint Cabinets in Fredericton, New Brunswick, we help homeowners, contractors and builders plan their kitchen cabinetry around these requirements before cabinets are ordered, helping avoid unnecessary renovation costs and installation problems.

Whether you are renovating your existing kitchen or building a new home, here is what you need to know before deciding which goes in first.

Should You Install Flooring or Kitchen Cabinets First?

The most important factor is whether your flooring is fixed to the subfloor or designed to float.

Fixed flooring can often be installed underneath kitchen cabinets, while floating flooring generally needs to be installed around them. Always follow the flooring manufacturer’s installation and warranty requirements. These take priority over general renovation recommendations.

Quick check

What flooring are you installing?

Flooring can usually go first

Ceramic and porcelain tile can generally be installed before kitchen cabinets when the tile and supporting subfloor are suitable for the installation.

Always follow the flooring manufacturer’s installation and warranty requirements. Read more
Flooring can usually go first

Traditional nail-down hardwood and certain glue-down engineered hardwood products can often be installed underneath kitchen cabinets.

Always follow the flooring manufacturer’s installation and warranty requirements. Read more
Often first, but confirm the product

Not all engineered hardwood is installed the same way. Confirm the installation method with your flooring supplier before finalizing your cabinet plans.

Always follow the flooring manufacturer’s installation and warranty requirements. Read more
Install cabinets first

Some products use a floating installation system, which generally requires fixed cabinetry to be installed first.

Always follow the flooring manufacturer’s installation and warranty requirements. Read more
Flooring can often go first

Fully adhered vinyl flooring can often be installed underneath kitchen cabinets because it is bonded directly to the subfloor.

Always follow the flooring manufacturer’s installation and warranty requirements. Read more
Install cabinets first

If you are installing click-lock luxury vinyl plank flooring, the recommended approach is generally to install and secure your kitchen cabinets first.

Always follow the flooring manufacturer’s installation and warranty requirements. Read more
Install cabinets first

Kitchen cabinets should normally be installed before the laminate, allowing the finished floor to expand and contract around the cabinetry.

Always follow the flooring manufacturer’s installation and warranty requirements. Read more

Which Flooring Types Can Go Under Kitchen Cabinets?

Ceramic and Porcelain Tile

Ceramic and porcelain tile can generally be installed before kitchen cabinets when the tile and supporting subfloor are suitable for the installation.

Installing tile across the entire kitchen offers several potential advantages:

  • Consistent finished floor height.
  • Greater flexibility for future cabinet layout changes.
  • Fewer complicated cuts around cabinet bases.
  • Easier coordination of appliance openings.

However, installing tile underneath cabinets requires additional flooring materials and labour. If the cabinet layout is unlikely to change, installing cabinets first may be a more economical option.

Hardwood and Engineered Hardwood

Traditional nail-down hardwood and certain glue-down engineered hardwood products can often be installed underneath kitchen cabinets.

Installing hardwood first can provide a consistent finished floor level and make future kitchen renovations easier.

However, not all engineered hardwood is installed the same way. Some products use a floating installation system, which generally requires fixed cabinetry to be installed first.

Confirm the installation method with your flooring supplier before finalizing your cabinet plans.

Glue-Down Vinyl Flooring

Fully adhered vinyl flooring can often be installed underneath kitchen cabinets because it is bonded directly to the subfloor.

Unlike floating vinyl plank, it does not rely on the same unrestricted movement across the floor.

For example, Armstrong Flooring permits cabinet installation over certain fully adhered Alterna engineered tile products, subject to its installation requirements.

The important distinction is not simply whether you are using vinyl flooring, but how that flooring is installed.

Can You Install Kitchen Cabinets Over Floating Flooring?

Fixed kitchen cabinets should generally not be installed directly over floating flooring.

Floating floors are designed to expand and contract as temperature and humidity change. Installing heavy, fixed cabinetry on top can restrict that movement and potentially damage the flooring.

Common problems include:

  • Buckling or raised flooring.
  • Separation between planks.
  • Damaged click-lock joints.
  • Uneven flooring surfaces.
  • Flooring warranty issues.

Floating Luxury Vinyl Plank (LVP)

If you are installing click-lock luxury vinyl plank flooring, the recommended approach is generally to install and secure your kitchen cabinets first.

The flooring is then installed around the cabinet bases, leaving the expansion gap specified by the flooring manufacturer.

Suitable toe-kick trim, shoe moulding or quarter round can conceal this gap without restricting floor movement.

Floating Laminate Flooring

Floating laminate follows the same general principle.

Kitchen cabinets should normally be installed before the laminate, allowing the finished floor to expand and contract around the cabinetry.

This is particularly important in homes where indoor temperature and humidity fluctuate throughout the year.

What About Kitchen Islands?

Fixed kitchen islands should generally be installed and secured before floating flooring.

An island can restrict flooring movement in the same way as perimeter kitchen cabinets, particularly when it is anchored to the subfloor.

If you are planning a kitchen island with additional storage, seating, plumbing or electrical connections, coordinate its position and installation requirements before flooring work begins.

How Flooring Thickness Affects Kitchen Cabinet Installation

Even when the correct installation order is followed, flooring thickness can affect the finished dimensions of your kitchen.

This is one of the most important details to address during cabinet planning.

Dishwasher and Appliance Clearance

Dishwashers are particularly sensitive to changes in finished floor height because they must fit between the floor and the underside of the countertop.

Consider this hypothetical example:

Hypothetical exampleHeight
Base cabinet height (before countertop)34½″
Cabinets installed directly on the subfloorOpening: 34½″
Flooring added afterwards, including into the dishwasher opening– ¾″
Finished opening under the countertop33¾″
Opening the dishwasher in this example requires34″
Result¼″ short

In this example, adding the flooring without adjusting the cabinet and countertop plan could leave insufficient clearance to install or remove the dishwasher.

Even a quarter-inch difference can create an expensive problem once the countertops are installed.

Try your own numbers

Dishwasher and countertop height check

Countertop height from finished floor–
Dishwasher opening height–
Clearance along the removal path–

A planning estimate only. Required opening heights vary by appliance, so use the dimensions in your dishwasher manufacturer’s installation guide.

Always confirm the appliance manufacturer’s required opening dimensions, the finished floor height inside the appliance opening and the clearance along its removal path.

Refrigerators and ranges should also be checked against the final cabinet layout and finished floor height.

Cabinet Height and Countertop Height

Standard kitchen base cabinets are typically 34½ inches tall before countertops are installed, although cabinet dimensions vary by product and design.

If the cabinets sit directly on the subfloor and the finished flooring is installed around them, the effective countertop height measured from the finished floor will be reduced by the flooring thickness.

This may not cause a significant issue with thinner flooring, but thicker tile, hardwood or flooring underlayment can make a noticeable difference.

Toe Kicks and Cabinet Trim

The recessed area underneath your base cabinets is known as the toe kick.

When flooring is installed after cabinets, the toe-kick and trim details need to accommodate the finished floor height and any required expansion gaps.

Planning these details early helps create a cleaner, more intentional finish without unnecessary gaps or oversized mouldings.

Planning Your Kitchen Before Ordering Cabinets?

Bring your kitchen measurements, appliance dimensions and flooring specifications to BluePrint Cabinets.

Our Fredericton team can help you plan your cabinet layout, storage requirements and finished dimensions before you commit to your renovation.

Discuss your kitchen project with our team

What Is the Correct Order for a Kitchen Renovation?

The installation sequence depends on your flooring product, cabinet design and overall renovation requirements.

Here are two common examples.

Kitchen Renovation With Floating Vinyl Plank

  1. Finalize the cabinet layout and appliance specifications.
  2. Remove existing cabinets and flooring.
  3. Complete necessary rough-in work and subfloor preparation.
  4. Install and secure kitchen cabinets and fixed islands.
  5. Coordinate countertop installation.
  6. Install floating flooring around the cabinetry, maintaining the required expansion gaps.
  7. Complete toe kicks, trim and appliance installation.

Kitchen Renovation With Tile Flooring

  1. Finalize the cabinet layout and appliance specifications.
  2. Remove existing cabinets and flooring.
  3. Complete necessary rough-in work and subfloor preparation.
  4. Install tile flooring and allow it to cure as required.
  5. Install kitchen cabinets over the finished tile.
  6. Install countertops.
  7. Complete appliances, toe kicks and finishing work.

Both approaches can produce a durable, attractive kitchen when the materials and installation sequence are properly coordinated.

Your cabinet supplier, flooring installer and renovation contractor should agree on the sequence before work begins.

What to Check Before Ordering Kitchen Cabinets

You do not need to have every decorative finish selected before starting your kitchen design, but you should confirm the following details before finalizing your cabinet order.

Kitchen Cabinet and Flooring Planning Checklist

These details are particularly important when coordinating multiple contractors or managing your own DIY kitchen renovation.

A well-planned cabinet layout considers more than storage and appearance. It also accounts for how the cabinetry fits with the other components of your home.

Frequently Asked Questions

Do you put flooring under kitchen cabinets?

You can often install tile, nail-down hardwood and fully adhered vinyl underneath kitchen cabinets. Floating vinyl plank, laminate and floating engineered hardwood should generally be installed around fixed cabinets instead.

Always confirm the flooring manufacturer’s requirements.

Should vinyl plank flooring go under kitchen cabinets?

Floating or click-lock vinyl plank flooring should generally not go underneath fixed kitchen cabinets. Fully adhered glue-down vinyl plank may be suitable, depending on the manufacturer’s installation instructions.

Should flooring go under a dishwasher?

The dishwasher opening should have a suitable, level supporting surface and enough finished clearance to allow the appliance to be installed and removed.

Whether the finished flooring extends underneath the dishwasher depends on the flooring product and appliance installation requirements.

Is it cheaper to install cabinets before flooring?

Installing cabinets first can reduce flooring material and labour costs because you are not covering areas concealed underneath the cabinetry.

However, the potential savings should be weighed against appliance clearance, installation requirements and the possibility of future cabinet layout changes.

Can you replace kitchen cabinets without replacing the flooring?

Yes, in many cases. However, changing the cabinet layout may expose unfinished subfloor or areas where the existing flooring is damaged or discoloured.

Keeping a similar cabinet footprint can make it easier to retain your existing flooring.

Does flooring go under bathroom vanities?

The same general principles apply to fixed bathroom vanities, pantry cabinets, laundry room cabinets and other built-in storage.

Fixed cabinetry should generally be installed before floating flooring, while suitable tile and fully adhered flooring may be installed underneath it.

Planning Your Kitchen Renovation in New Brunswick?

Getting the installation order right starts with planning your kitchen before materials are ordered and renovation work begins.

At BluePrint Cabinets, we help homeowners, contractors, builders and DIY renovators across Fredericton and New Brunswick find practical cabinetry solutions that balance durability, functionality and value.

Our cabinetry options include:

Our cabinet offerings include durable construction features such as 5/8-inch plywood cabinet boxes and 3/4-inch solid birch face frames, with transparent pricing and typical delivery within two to four weeks of ordering.

While we do not install flooring, we can help you account for flooring thickness, appliance spacing, cabinet dimensions and layout requirements during the cabinet planning process.

Visit our Fredericton cabinet showroom or contact BluePrint Cabinets to discuss your next kitchen renovation.

Bring your measurements, flooring specifications and design ideas. We will help you plan cabinetry that works with your renovation from the start.